Work Breakdown Structure (WBS)
The WBS focuses on prototype development of all three innovation goals plus
use-case, training, and user-community work. Hardware procurement and 24×7
production operations are out of scope; both are deferred to the follow-on
operations proposal.
Phase 1 — Prototype Development (Months 1–12)
WBS
Work Package
Lead
1.0
Platform Software Prototype (IaC, Kubernetes on Jetstream-2, PostgreSQL/DuckLake, CI/CD, validation)
Roberts (Lead RSE)
2.0
AI/ML Prototype (Goal 3): vLLM, model evaluation, RAG, MCP framework, sandbox, multi-agent orchestration
Roberts; GRA 1
3.0
Data Mesh Prototype (Goal 2, RENCI-led): zone analysis, policy-engine design & prototype, federation testing, Lakehouse–Mesh integration
Russell (RENCI Co-PI); GRA 3 (ECE Security)
4.0
Lakehouse Prototype (Goal 1): schema, DuckLake/Iceberg prototype, time-travel versioning, query optimization, Iceberg/Parquet integration
Cao (Co-PI); Choi; GRA 2 (CS DB)
Phase 2 — Science-Case and User-Community Maturation (Months 12–18)
WBS
Work Package
Lead
5.0
Use-Case Implementation: UC1 Agentic Discovery + Multi-Omics; UC2 Geospatial + EHT prototype pipeline; UC3 IoT prototype
Roberts, Chism, Swetnam, Chan, Chen
6.0
Early-Adopter Onboarding: ESIIL, NCEMS, AIIRA; ACCESS-CI integration; TrustedCI prototype security review
Chism, Swetnam, Edgin, Skidmore, GRA 3
7.0
Training & Documentation: technical docs, user training, 8 workshops, 8 Educator Fellows
Chism, Jentner, GRAs
Phase 2 (continued) — Sustainability & Follow-On Proposal (Months 18–24)
WBS
Work Package
Lead
8.0
Empirical Hardware Specification & Cost Model: prototype benchmarking, hardware-spec derivation, cost-recovery model, follow-on proposal preparation
Swetnam, Cao, Russell, Edgin
9.0
Best-Effort User Support & Community Growth: Tier-½ support, community engagement, ≥8 letters of support
Project Ops Mgr, GRAs, Chism, all senior personnel
Critical Path
28 weeks of unbroken dependency in Phase 1:
Weeks 1–6 — IaC template development (Roberts, Edgin)
Weeks 3–10 — Kubernetes deployment on Jetstream-2 (Roberts, Edgin)
Weeks 5–16 — PostgreSQL/DuckLake prototype (Choi, Cao, Roberts)
Weeks 5–36 — vLLM / RAG / MCP prototype (Roberts, GRA 1)
Weeks 2–24 — iRODS policy-engine prototype (Russell, RENCI RSEs, GRA 3)
Weeks 24–48 — End-to-end Lakehouse–Mesh integration (Cao, Edgin, Russell)
Key Dependencies
All software prototypes (WBS 1.0–4.0) deploy on leveraged Jetstream-2 /
CyVerse / UA HPC — no hardware-procurement dependency .
AI/ML prototype (WBS 2.0) depends on Kubernetes deployment (WBS 1.2)
being available by Week 10.
Use-case implementation (WBS 5.0) depends on Phase 1 prototype completion
(Month 12 milestone).
Early-adopter onboarding (WBS 6.0) depends on prototype validation (WBS 1.5).
Empirical hardware specification (WBS 8.0) depends on benchmarking against
Phase 1–2 prototype performance.