Schedule & Milestones

High-level phase schedule

Phase Description Months
1 Prototype development on leveraged infrastructure 1–12
2 Science-case + user-community maturation 12–18
2 (continued) Sustainability + follow-on proposal preparation 18–24

Period of performance: June 1, 2026 – May 31, 2028.

Major milestones (baseline)

ID Milestone Target Month Owner
M1.1 Project kickoff; baselined PEP filed; CCB chartered 1 PI
M1.2 IaC templates published; Kubernetes on Jetstream-2 operational 3 Roberts
M1.3 Lakehouse prototype (Goal 1) end-to-end on benchmark data 6 Cao
M1.4 Data Mesh prototype (Goal 2) — first federated zone 8 Russell
M1.5 Agentic AI prototype (Goal 3) — MCP + vLLM + RAG end-to-end 10 Roberts
M1.6 Phase 1 prototype demonstrated end-to-end on leveraged infrastructure 12 PI
M2.1 UC1 (Agentic Discovery + Multi-Omics) reproducible workflow + DOI 15 Roberts, Chism
M2.2 UC2 (Geospatial + EHT sub-PB demo) reproducible workflow + DOI 17 Chan
M2.3 UC3 (IoT / Edge) reproducible workflow + DOI 18 Chen
M3.1 Empirical hardware specification published 22 Swetnam, Cao, Russell, Edgin
M3.2 ≥ 8 letters of support secured 23 Project Ops Mgr
M3.3 Submission-ready follow-on Cat I/II operations proposal package 24 PI

Schedule contingency

The Y1-front-loaded staffing pattern provides 24-month personnel continuity even if some staff turn over in Y2. RENCI's reduced 25% Y2 staffing buys ~2 months of slack against policy-engine timeline slip.

Reporting cadence

  • Weekly — UA-side stand-up; RENCI-side stand-up
  • Monthly — Combined UA + RENCI status review; CCB
  • Quarterly — PI ↔ Co-PI Russell status meeting; NSF program officer check-in (informal)
  • Twice-yearly — External AI Ethics Advisory Board review
  • Annually — NSF annual report; full project review with all stakeholders
  • Final — NSF final report at Month 24; follow-on-proposal submission